Construction Starting Next Week for 2480 Bancroft Way, Berkeley

2480 Bancroft Way new design, rendering by Studio KDA2480 Bancroft Way new design, rendering by Studio KDA

The development team tells YIMBY that construction will start next week for the eight-story apartment at 2480 Bancroft Way in Southside, Berkeley. The Edge, as it is called, will overlook the UC Berkeley Campus by the busy Telegraph Avenue intersection. Ruegg & Ellsworth is the project developer.

Studio KDA is responsible for the design. The infill-style building will conform to most of the lot, with its primary north-facing facade carved by three private decks. Additional articulation will visually break up the east and west facades. The sidewalk improvements and rooftop deck will be designed by 122 West Landscape Architecture.

2480 Bancroft Way rooftop deck, rendering by Studio KDA

2480 Bancroft Way rooftop deck, rendering by Studio KDA2480 Bancroft Way rooftop deck, rendering by Studio KDA

The developer has used the State Density Bonus program to increase residential capacity to 28 units. Two of the four-bedroom units will designated as affordable to very low-income households. Parking will be included for 56 bicycles. The 83-foot tall structure will yield around 37,500 square feet, including an amenity rooftop deck and roughly 2,000 square feet for retail. The developer is expecting the space to be occupied by a future restaurant.

The property is located along Bancroft Way between Telegraph Avenue and Dana Street. Future residents will be across from the UC Berkeley campus and half a block from the busy retail-rich Telegraph Avenue thoroughfare. BKF is the civil engineer.

2480 Bancroft Way, image by Google Street View

2480 Bancroft Way, image by Google Street View

WEST Builders is the general contractor. Construction will start with demolition and site grading. Concrete work is scheduled to start in December, with framing to rise from March of 2024 to the end of the year. Completion is expected by Summer 2025. A representative for the developer shared with YIMBY, “we’re very excited. This project has not skipped a beat.”

Subscribe to YIMBY’s daily e-mail

Follow YIMBYgram for real-time photo updates
Like YIMBY on Facebook
Follow YIMBY’s Twitter for the latest in YIMBYnews

.

Be the first to comment on "Construction Starting Next Week for 2480 Bancroft Way, Berkeley"

Leave a comment

Your email address will not be published.


*